September 4, 2006
Work Activities this Week - Site Work: Sanitary Sewer Lines, Storm Drainage, Water Distribution System, Site Grading
- Floor 1: Electrical Trim / Terminations, Finish Carpentry & Millwork, Fire Protection Trim
- Floor 2: Lighting Fixtures, Plumbing Fixtures & Trim, HVAC Trim, Electrical Trim / Terminations, Fire Protection Trim
- Floor 3: Painting, Electrical Trim / Terminations, Plumbing Fixtures & Trim
- Floor 4: Hang / Tape / Finish Sheet Rock, Painting
- Floor 5: Fireproofing, Rough Carpentry, Interior Framing, HVAC Rough-In (RI), Plumbing RI, Hollow Metal Door Frames, Electrical RI at Walls, Mechanical Insulation
- Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, Metal Roof Panels / Flashing & S.M.
- Building - All Floors: Automatic Controls System, Metal Railings