September 25, 2006
Work Activities this Week - Site Work: Sanitary Sewer Lines, Storm Drainage, Water Distribution System, Site Grading, Fire Department Connection
- Floor 1: No work this week
- Floor 2: Special Wall Surfaces - FRP Panels, Seismic - Expansion Joints / Sheetrock, Cabinets - Plastic Laminate Faced, Seismic - Acoustical Grid Patch, Finish Carpentry and Millwork
- Floor 3: Electrical Trim / Terminations, Acoustical Ceiling Grid, Fire Protection Trim, Lighting Fixtures, Ceramic Tile, Special Wall Surfaces - FRP Panels, Cabinets - Plastic Laminate Faced, HVAC Trim, Plumbing Fixtures and Trim, Finish Carpentry and Millwork
- Floor 4: Hang / Tape / Finish Sheetrock, Painting, Ceramic Tile, Electrical Trim / Terminations, Special Wall Surfaces - FRP Panels, Acoustical Ceiling Grid, Plumbing Fixtures and Trim, Cabinets - Wood Faced
- Floor 5: Interior Framing, HVAC Rough-In (RI), Hollow Metal Door Frames, Rough Carpentry, Electrical RI at Walls, Hang / Tape / Finish Sheetrock, Insulation - Batt, Install Mechanical Equipment
- Roof / Building Envelope: Exterior Walls Insulation (Batt and Rigid), Hardiboard at at Parapet - Interior Side, Weather - Resistive Barrier (Tyvek), Masonry, Windows, Metal Roof Panels / Flashing and S.M.
- Building - All Floors: Hydraulic Elevator Installation, Automatic Controls System, Metal Railings, Fire Alarm System - Trim and Finish, Telephone and Data Systems, Fire Extinguishers and Cabinets