September 18, 2006

      Work Activities this Week

  • Site Work: Water Distribution System
  • Floor 1: Finish on Wood Trim, Finish Carpentry & Millwork
  • Floor 2: Special Wall Surfaces-FRP Panels, Cabinets-Plastic Laminate Faced
  • Floor 3: Hang / Tape / Finish Sheetrock, Electrical Trim / Terminations, Acoustical Ceiling Grid, Lighting Fixtures, Ceramic Tile, Cabinets-Plastic Laminate Faced, HVAC Trim
  • Floor 4: Hang / Tape / Finish Sheetrock, Painting, Ceramic Tile
  • Floor 5: HVAC Rough-In (RI), Plumbing RI, Fire Protection RI, Electrical RI at Walls, Seismic - Expasion Joints
  • Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (TYVEK), Masonry, Metal Roof Panels / Flashing & S.M.
  • Building - All Floors: Hydraulic Elevator Installation, Automatic Controls System, Metal Railings

 

 

 