September 18, 2006
Work Activities this Week - Site Work: Water Distribution System
- Floor 1: Finish on Wood Trim, Finish Carpentry & Millwork
- Floor 2: Special Wall Surfaces-FRP Panels, Cabinets-Plastic Laminate Faced
- Floor 3: Hang / Tape / Finish Sheetrock, Electrical Trim / Terminations, Acoustical Ceiling Grid, Lighting Fixtures, Ceramic Tile, Cabinets-Plastic Laminate Faced, HVAC Trim
- Floor 4: Hang / Tape / Finish Sheetrock, Painting, Ceramic Tile
- Floor 5: HVAC Rough-In (RI), Plumbing RI, Fire Protection RI, Electrical RI at Walls, Seismic - Expasion Joints
- Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (TYVEK), Masonry, Metal Roof Panels / Flashing & S.M.
- Building - All Floors: Hydraulic Elevator Installation, Automatic Controls System, Metal Railings