Construction Updates

October  30, 2006

      Work Activities this Week

  • Site Work: Site Grading, Curbs and Partial Sidewalks, Site Electrical Rough In (RI) for Site Lighting, Site Lighting & Trims, Place & Compact Gravel for Grass Pavers & Set Units & Topsoil
  • Floor 1: No work this week
  • Floor 2: Finish Carpentry & Millwork, Aluminum Flush Doors, Auditorium Seating With Electrical
  • Floor 3: Finish Carpentry & Millwork
  • Floor 4: Electrical Trim / Terminations, Fire Protection Trim, HVAC Trim, Finish Carpentry & Millwork
  • Floor 5: Hang / Tape / Finish Sheetrock, Fire Protection RI, Electrical Trim / Terminations
  • Roof / Building Envelope: Exterior Walls Insulation (Batt & Rigid). Weather - Resistive Barrier (Tyvek), Masonry, GFRC Cornice, GFRC Columns & Cornice, F/P Concrete Sog at S & W
  • Building - All Floors: Automatic Controls System, Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Toilet Compartments, Acoustical Ceiling Tile, Wood Doors / Finish Hardware, Sealants & Caulking, Toilet Accessories, Carpet, Interior Glass & Glazing, Residential Appliances

 

 

 

Previous construction updates

Page maintained by Dorita Tessier
Last update on November 28, 2006