October  23, 2006

      Work Activities this Week

  • Site Work: Site Grading, Place & Compact Gravel for Grass Pavers, Set Units & Topsoil
  • Floor 1: No work this week
  • Floor 2: Finish Carpentry & Millwork, Aluminum Flush Doors
  • Floor 3: Finish Carpentry & Millwork
  • Floor 4: Electrical Trim / Terminations, Cabinets - Wood Faced, Lighting Fixtures, HVAC Trim, Finish Carpentry & Millwork
  • Floor 5: Hang / Tape / Finish Sheetrock, Painting, Fire Protection Rough-In (RI), HVAC Trim, Electrical Trim / Terminations
  • Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, GFRC Cornice, Louvers & Vents at Roof / Towers, GFRC Columns & Cornice
  • Building - All Floors: Automatic Controls System, Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Toilet Compartments, Acoustical Ceiling Tile, Wood Doors / Finish Hardware, Sealants & Caulking, Start Up HVAC Unit, Carpet

 

 

 