October 23, 2006
Work Activities this Week - Site Work: Site Grading, Place & Compact Gravel for Grass Pavers, Set Units & Topsoil
- Floor 1: No work this week
- Floor 2: Finish Carpentry & Millwork, Aluminum Flush Doors
- Floor 3: Finish Carpentry & Millwork
- Floor 4: Electrical Trim / Terminations, Cabinets - Wood Faced, Lighting Fixtures, HVAC Trim, Finish Carpentry & Millwork
- Floor 5: Hang / Tape / Finish Sheetrock, Painting, Fire Protection Rough-In (RI), HVAC Trim, Electrical Trim / Terminations
- Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, GFRC Cornice, Louvers & Vents at Roof / Towers, GFRC Columns & Cornice
- Building - All Floors: Automatic Controls System, Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Toilet Compartments, Acoustical Ceiling Tile, Wood Doors / Finish Hardware, Sealants & Caulking, Start Up HVAC Unit, Carpet