October  2, 2006

      Work Activities this Week

  • Site Work: Storm Drainage, Water Distribution System, Site Grading, Fire Department Connection
  • Floor 1: No work this week
  • Floor 2: Finish Carpentry and Millwork
  • Floor 3: Electrical Trim / Terminations, Finish Carpentry and Millwork
  • Floor 4: Electrical Trim / Terminations, Acoustical Ceiling Grid, Lighting Fixtures, Finish Carpentry and Millwork
  • Floor 5: Electrical Rough-In (Pull Wire), Hang / Tape / Finish Sheetrock
  • Roof / Building Envelope: Exterior Walls Insulation (Batt and Rigid), Weather-Resistive Barrier (Tyvek), Masonry, Metal Roof Panels / Flashing and S.M.
  • Building - All Floors: Hydraulic Elevator Installation, Automatic Controls System, Metal Railings, Fire Alarm System - Trim and Finish, Telephone and Data Systems, Toilet Compartments, Fire Extinguishers and Cabinets, Visual Display

 

 

 