Construction Updates

October  16, 2006

      Work Activities this Week

  • Site Work: Site Grading, Fire Department Connection
  • Floor 1: Finish Carpentry & Millwork
  • Floor 2: Aluminum Flush Doors
  • Floor 3: Electrical Trim / Terminations, Lighting Fixtures, Finish Carpentry & Millwork
  • Floor 4: Electrical Trim / Terminations, Fire Protection Trim, Lighting Fixtures, HVAC Trim
  • Floor 5: HVAC Rough-In (RI), Electrical RI (Pull Wire), Hang / Tape / Finish Sheetrock, Install Mechanical Equipment
  • Roof / Building Envelope: Exterior Wall Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, GFRC Cornice, Louvers & Vents at Roof / Towers
  • Building - All Floors: Automatic Controls System, Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Toilet Compartments, Projection Screens, Acoustical Ceiling Tile, Wood Doors / Finish Hardware, Sealants & Caulking

 

 

 