November 6, 2006
Work Activities this Week - Site Work: Site Grading, Curbs and Partial Sidewalks, Place & Compact Gravel for Grass Pavers & Set Units & Topsoil
- Floor 1: No work this week
- Floor 2: Finish Carpentry & Millwork, Aluminum Flush Doors, Auditorium Seating With Electrical
- Floor 3: Finish Carpentry & Millwork
- Floor 4: Electrical Trim / Terminations, Finish Carpentry & Millwork
- Floor 5: Painting, Fire Protection Rough In (RI), Electrical Trim / Terminations
- Roof / Building Envelope: Exterior Walls Insulation (Batt & Rigid), Weather - Resistive Barrier (Tyvek), Masonry, GFRC Cornice, GFRC Columns & Cornice, F / P Concrete Sog at S & W
- Building - All Floors: Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Resilient Flooring - VCT / SHT Vinyl, Wood Doors / Finish Hardware, Toilet Accessories, Carpet, Interior Glass & Glazing, Residential Appliances