November 27, 2006
Work Activities this Week - Site Work: Site Grading, Curbs & Partial Sidewalks, Site Electrical Rough In (RI) for Site Lighting, Remainder of Sidewalks, Concrete Stairs, Place & Compact Gravel for Grass Pavers / Set Units / Topsoil
- Floor 1: No work this week
- Floor 2: Finish Carpentry & Millwork, Aluminum Flush Doors
- Floor 3: No work this week
- Floor 4: Electrical Trim / Terminations, Lighting Fixtures, Finish Carpentry & Millwork
- Floor 5: No work this week
- Roof / Building Envelope: Exterior Walls Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, Metal Roof Panels / Flashing & S.M., GFRC Cornice, GFRC Columns & Cornice, F / P Concrete Sog at S & W, Remove Scaffolding, EPDM Roofing - Porch Roofs, Tower Clock & Remote Control
- Building - All Floors: Metal Railings, Telephone & Data Systems, Resilient Flooring - VCT / SHT Vinyl, Acoustical Ceiling Tile, Wood Doors / Finish Hardware, Sealants & Caulking, Carpet, Residential Appliances, Testing / Balancing / Adjusting