November 20, 2006
Work Activities this Week - Site Work: Site Grading, Curbs & Partial Sidewalks, Site Electrical Rough In (RI) For Site Lighting, Remainder of Sidewalks, Place & Compact Gravel for Grass Pavers / Set Units / Topsoil
- Floor 1: No work this week
- Floor 2: Aluminum Flush Doors
- Floor 3: Finish Carpentry & Millwork
- Floor 4: Electrical Trim / Terminations, Finish Carpentry & Millwork
- Floor 5: Painting
- Roof / Building Envelope: Exterior Walls Insulation (Batt & Rigid), Weather-Resistive Barrier (Tyvek), Masonry, Metal Roof Panels / Flashing & S.M., GFRC Cornice, GFRC Columns & Cornice, F/P Concrete Sog at S & W, Remove Scaffolding
- Building - All Floors: Automatic Controls System, Metal Railings, Fire Alarm System - Trim & Finish, Telephone & Data Systems, Resilient Flooring - VCT / SHT Vinyl, Toilet Compartments, Wood Doors / Finish Hardware, Sealants & Caulking, Carpet, Interior Glass & Glazing, Residential Appliances, Testing / Balancing / Adjusting for HVAC
Previous construction updates
|
WHAT'S HAPPENING
|