      Work Activities this Week

  • Floor 1: Batt Insulation
  • Floor 2: Batt Insulation
  • Floor 3: Rough Carpentry
  • Floor 4: Hollow Metal Door Frames, Rough Carpentry, Rough-Ins: Fire Protection, Electrical
  • Floor 5: Structural Framing, Rough-Ins: HVAC

 

 

 