      Work Activities this Week

  • Floor 1: Fluid applied water-proofing, Backfill and compact at building, Hang/tape/finish Sheet Rock
  • Floor 2: Rough carpentry
  • Floor 3: Rough carpentry, Hollow metal door frames, Rough-ins: Electrical, Fire protection
  • Floor 4: Interior framing, Rough-ins: HVAC, Plumbing
  • Floor 5: Rough-ins: HVAC, Plumbing
  • Roof/Building Envelope: Steel deck at roof, Miscellaneous steel at roof
  • Building-All Floors: Hydraulic elevator installation, Set elevator jack

 

 

 