March 27, 2006

     Work Activities This Week

  • Sanitary sewer lines on the west side completed
  • Worked on footings, slab and foundation walls for the utility tunnel
  • Floor 1 - Waterproofing applied, backfill and compacting at building, plumbing rough-in, interior framing, HVAC rough-in, mechanical insulation
  • Floor 2 - Ran top track of steel, structural framing, fire proofing, interior framing, plumbing rough-in, electrical rough-in
  • Floor 3 - Run top track steel, structural framing, plumbing rough-in, electrical rough-in
  • Floor 4 - Placed concrete in elevator shaft wall, mechanical & electrical rough-in at steel deck
  • Floor 5 - Steel erection, steel deck 