Construction Updates

March 20, 2006

      Work Activities this Week

  • Set unistrut rack and mechanical rough-in for the utility tunnel
  • Floor 1 - Back fill and compacting at building, interior framing, HVAC rough-in, plumbing rough-in, electrical rough-in
  • Floor 2 - Ran top track of steel, fire proofing, interior framing, plumbing and electrical rough-in
  • Floor 3 - Plumbing and electrical rough-in
  • Floor 4 - worked on forming and rebar for the elevator shaft wall
  • Floor 5 - Installed steel deck and metal stairs

 

 