      Work Activities this Week

  • Floor 1: Painting Walls
  • Floor 2: Hang/Tape/Finish Sheet Rock
  • Floor 3: Hang/Tape/Finish Sheet Rock, Rough-In: Electrical (pull wire)
  • Floor 4: Hollow Metal Door Frames, Hang/Tape/Finish Sheet Rock, Rough-In: Electrical (pull wire)
  • Floor 5: Metal Ladders (backing), Interior Framing, Rough-In: Plumbing
  • Roof / Building Envelope: Pour Slabs for Porches
  • Building - ALL FLOORS: Metal Railings

 

 

 