Construction Updates

February 13, 2006

  • Forming tunnel walls for 65 feet of utility tunnel
  • Forming elevator shaft walls for the 3rd to 4th floors
  • 1st floor ready for concrete slab
  • Steel erection complete to above 3rd floor
  • Steel decking complete for 2nd and 3rd floors

 

 

 