Construction Updates

December 12, 2005

  • Completed manhole for the sewer lines on the west side
  • Backfilling around the storm drain on the west side
  • Continued forming footings, grade beams and foundation walls, installing rebar and placing concrete.  Placed first foundation wall concrete 