December 11, 2006
Work Activities this Week - Site Work: Site Grading, Curbs and Partial Sidewalks, Site Electrical Rough-In (RI) for Site Lighting, Asphalt Pavement, Remainder of Sidewalks, Concrete Stairs, Site Lighting & Trims, Place & Compact Gravel for Grass Pavers & Set Units & Topsoil, Site Signage
- Floor 1: No work this week
- Floor 2: Finish Carpentry & Millwork, Auditorium Seating w/ Electric
- Floor 3: Finish Carpentry & Millwork
- Floor 4: Electrical Trim / Terminations
- Roof / Building Envelope: Metal Roof Panels / Flashing & S.M., GRFC Cornice, GFRC Columns & Cornice, F / P Concrete Sog at S & W, EPDM Roofing - Porch Roofs
- Building - All Floors: Metal Railings, Telephone & Data Systems, Resilient Flooring - VCT / SHT Vinyl, Wood Doors / Finish Hardware, Sealants & Caulking, Access Doors, Carpet, Horizontal Louver Blinds, Interior Glass & Glazing, Entry Mat, Residential Appliances, Testing & Balancing & Adjusting, Final Cleaning