Construction Updates

August 21, 2006

      Work Activities this Week

  • Site Work: Sanitary Sewer Lines
  • Floor 1: Plumbing Fixtures and Trim, HVAC Trim, Electrical Trim / Terminations, Fire Protection Trim
  • Floor 2: Lighting Fixtures, Plumbing Fixtures and Trim, HVAC Trim, Electrical Trim / Terminations, Fire Protection Trim
  • Floor 3: Painting
  • Floor 4: Hang / Tape / Finish Sheet Rock
  • Floor 5: Fire Proofing, Interior Framing, Seismic - Expansion Joints
  • Roof / Building Envelope: Exterior Wall Insulation (Batt and Rigid), Weather-Resistive Barrier (Tyvek), Masonry, Windows, Metal Roofing Panels / Flashing 
  • Building / All-Floors: Hydraulic Elevator Installation, Seismic - Add deck at Elevator, Metal Railings

 

 

 