Construction Updates

August 14, 2006

      Work Activities this Week

  • Site Work: Sanitary Sewer Lines, Storm Drainage
  • Floor 1: Ceramic Tile (Grouted Tile), Plumbing Fixtures and Trim, HVAC Trim(Started this Week), Electrical Trim / Terminations
  • Floor 2: Ceramic Tile (Grouted Tile), Lighting and Fixtures, Plumbing Fixtures and Trim (Started this Week), HVAC Trim (Started this Week), Electrical Trim / Terminations 
  • Floor 3: Painting
  • Floor 4: Hang / Tape / Finish Sheet Rock
  • Floor 5: Rough Carpentry, Interior Framing
  • Roof / Building Envelope: Exterior Wall Insulation (Batt and Rigid), Weather-Resistive Barrier (TyVek), Masonry, Windows
  • Building-ALL FLOORS: Hydraulic Elevator Installation, Glass and Glazing, Metal Railings

 

 

 