Construction Updates

April 3, 2006

      Work Activities this Week

  • Utility Tunnel - FIP footings, Slab, Foundation walls (placed concrete for last walls on 4/5), Steel deck
  • Floor 1 - Backfill and compact at building, Interior framing, Mechanical insulation, Rough-ins: HVAC, Fire Protection, Electrical
  • Floor 2 - Interior framing, Mechanical insulation, Rough-ins: HVAC, Plumbing, Electrical
  • Floor 3 - Interior framing, Rough-ins: Plumbing, Electrical
  • Floor 4 - Mechanical/Electrical rough-in at steel deck, Pour slab on deck (placed concrete slab 4/7), Rough-ins: Plumbing, Electrical
  • Floor 5 - F/P CIP elevator shaft wall (placed concrete 4/6)

 

 

 