      Work Activities This Week

  • Utility Tunnel - Backfill and compact at tunnel, Rough-ins: Mechanical, Electrical
  • Floor 1 - Backfill and compact at building, Hollow metal door frames
  • Floor 2 - Hollow metal door frames, Rough-ins: Fire Protection, Electrical
  • Floor 3 - Interior framing, Mechanical insulation, Rough-ins: HVAC, Plumbing
  • Floor 4 - Structural framing, Interior framing, Rough-ins: Plumbing
  • Floor 5 - Steel erection, Steel deck, Pour slab on deck (placed concrete deck 4/27), Rough-ins at steel deck: Mechanical, Electrical
  • Roof/Building Envelope -  Frame towers, Mansards, Roof, Misc. steel at roof

 

 

 