April 24, 2006
Work Activities This Week - Utility Tunnel - Backfill and compact at tunnel, Rough-ins: Mechanical, Electrical
- Floor 1 - Backfill and compact at building, Hollow metal door frames
- Floor 2 - Hollow metal door frames, Rough-ins: Fire Protection, Electrical
- Floor 3 - Interior framing, Mechanical insulation, Rough-ins: HVAC, Plumbing
- Floor 4 - Structural framing, Interior framing, Rough-ins: Plumbing
- Floor 5 - Steel erection, Steel deck, Pour slab on deck (placed concrete deck 4/27), Rough-ins at steel deck: Mechanical, Electrical
- Roof/Building Envelope - Frame towers, Mansards, Roof, Misc. steel at roof