Construction Updates

April 17, 2006

      Work Activities This Week

  • Utility Tunnel - Set unistrut rack, Slab on deck (placed tunnel concrete top deck 4/17), Rough-ins: Mechanical, Electrical
  • Floor 1 - Fluid applied waterproofing, Backfill and compact at building, Rough-ins: Fire protection, Electrical, Electrical (wire and cable)
  • Floor 2 - Mechanical Installation, Rough-ins: HVAC, Plumbing
  • Floor 3 - Interior framing, Rough-ins: HVAC, Plumbing
  • Floor 4 - Structural framing, Rough-ins: Plumbing
  • Roof/Building Envelope - Steel deck at roof, Frame towers, Mansards, Roof

 

 

 